Andrew Marvell

Project Timeline

Andrew Marvell Business and Enterprise College is to be rebuilt on the current site, with students staying on site during the build programme as the school is part demolished in phases.

A single, four-storey block, will replace the separate individual buildings at the school, reducing the time spent travelling between lessons and overall making the running of the school much more efficient.

As an already well-used community school, the new building will enhance interaction with the public, through theatre space, drama and dance studios, a fitness suite and a library. There will also be a six-court sports hall and a floodlit all-weather pitch. Family services and a customer service centre will also be provided as part of the new school.

May 2011
  • Form school walkways and temporary car park
  • Asbestos survey and removal
  • Erect site hoarding
June 2011
  • Service diversions
  • Demolition
  • Site set-up installation
July 2011
  • Reduced level dig
  • Piling mat
  • Piling
August 2011
  • Construct pilecaps and groundbeams
  • Commence drainage installation
  • Commence steel frame
September 2011
  • Continue drainage installation
  • Continue steel frame
October 2011
  • Continue steel frame
  • Commence roof construction
  • Commence building envelope
November 2011
  • Install ETFE rooflights
  • Continue building envelope
  • Complete steel frame
View Images
December 2011
  • Internal services and finishes to sports hall area
  • Complete roof
  • Continue building envelope
January 2012
  • Roofing works completed
  • Masonry commences
  • Underfloor heating commences
February 2012
  • Continue Incoming services
  • Internal services and finishes to all areas
View Images
March 2012
  • Internal services and finishes to all areas
April 2012
  • Internal services and finishes to all areas
May 2012
  • Internal services and finishes to all areas
  • £50m ordered through Morgan Sindall Hull Companies
June 2012
  • Internal services and finishes to all areas
  • Commence hard landscaping
  • Install time capsule
July 2012
  • Internal services and finishes to all areas
  • Continue hard landscaping
  • Commence works to existing sports pitches
August 2012
  • Internal services and finishes to all areas
  • Continue hard landscaping
  • Continue works to existing sports pitches
  • 100th apprentice employed on Morgan Sindall Hull BSF Schemes
September 2012
  • Commence building commissioning
  • Commence building ICT infrastructure
  • Commence soft landscaping
  • Sample Schemes 1 year anniversary
October 2012
  • Continue building commissioning
  • Continue building ICT infrastructure
  • Continue soft landscaping
November 2012
  • Completion of landscape works
  • ICT equipment installation
December 2012
  • Decant school over to new building
  • Building handover
January 2013
  • School SAD
  • Demolition of existing school building commences