Project Timeline

Archbishop Sentamu Academy is a new kind of school for a new age, sponsored by the Church of England Diocese of York and dedicated to providing a 21st century learning environment that expands choices and opportunities for its students. The school is inclusive with a strong Christian ethos and welcomes students from all backgrounds, regardless of ability.

"Archbishop Sentamu Academy - the first of Hull's schools to be, the school to be!"

The new Archbishop Sentamu Academy on Preston Road was completed and opened on time. Now sitting alongside the Freedom Centre, it continues to specialise in Health Sciences and Business & Enterprise. Archbishop Sentamu is an eco-friendly school taking advantage of renewable and other 'green' technologies such as biomass generation for heating and harvesting rainwater for flushing toilets.

The new school is packed full of state-of-the-art computers and has a large focus on the high-tech facilities it offers to pupils.

January 2010
  • Pre-construction: the first visit to the site reveals a number of hurdles to overcome before the construction can begin
  • Demolition: part of the preparation includes the demolition of houses on the site
View Images
February 2010
  • Excavation: the first excavation on site begins as the substructure is prepared
  • Haul road: a new haul road is formed for construction vehicles to access the site
  • Piling: piling begins on site
View Images
March 2010
  • Energy Centre: piling is completed on the energy centre, ready to be cut down
  • Temporary accommodation: the temporary accommodation arrives on site
  • Foundations: work continues on the foundations as the site nears the start of the framework installation
View Images
April 2010
  • Main carpark: the site for the main car park is prepared
  • Structure: the first section of the steel structure rises from the foundations
  • Piling and steel structure: Piling continues, whilst the steel structure continues to take shape
View Images
May 2010
  • Riser installation: risers are lifted into place by crane and installed throughout the structure
  • Stairs: stairs between the school's floors are installed
  • Steel structure: The structure rises higher as the uppermost steelwork is put in place
View Images
June 2010
  • Roof steelwork completed: as the structure nears completion, the steelwork on the roof is completed
  • Excavation: excavation is underway for the playing fields and sports pitches
  • Foundations for vocational areas/sports hall; the foundations are laid
View Images
July 2010
  • Screeding: screeding begins throughout the ground floor
  • Staircases: Staircase construction is completed
View Images
August 2010
  • Roof: The roof structure makes good progress
  • Agora: The agora continues to take shape
  • Agora Roof: The roof of the agora starts to develop
View Images
September 2010
  • Cladding: Cladding begins on the outside of Archbishop Sentamu Academy
  • Sports Pitches: The laying of the sports pitches is complete
  • Insulation/Partitions: Rooms begin to take shape as insulation and partitions are installed
View Images
October 2010
  • Cladding 50%
  • 1st Floor Partitions
  • 1st Floor 1st Fix M&E
  • 3rd Floor UFH
View Images
November 2010
  • Cladding Complete
  • Windows Complete
  • Roof Complete
  • 2nd Floor 1st Fix M&E
View Images
December 2010
  • 4th Floor Screed Complete
  • 1st floor M&E 2nd fix
  • Power on
View Images
January 2011
  • Ground Floor Final Fix M&E
  • MUGA
View Images
February 2011
  • Lift Installation commence
  • Decoration 1st Floor
  • Section 278 works commence to Bilton Grove
View Images
March 2011
  • 3rd Floor M&E Final Fix
  • 4th Floor M&E 2nd Fix
  • Kitchen Fit Out
View Images
April 2011
  • Loose Furniture
  • Soft Floor Finishes 2nd Floor
  • Joinery
View Images
May 2011
  • 3rd Floor Soft Floor Finishes
  • 4th Floor Ceiling
  • Internal Signage
View Images
June 2011
  • Commissioning
View Images
July 2011
  • Commissioning
View Images
August 2011
  • Commissioning
View Images
September 2011
  • Archbishop Sentamu Academy is officially handed over as complete
  • Archbishop Sentamu Academy opens for the new school year