all projects

Other Projects

Endike Primary School

Project Timeline

Located in the North East of the city, the school can be found in parkland on Endike off Beverley Road, approximately 10km from the city centre. The school recently celebrated its 75th birthday, and the proposed development will transform Endike Primary into a 21st century school.

The proposals will provide a new school for the main school roll of 315 pupils, plus a 26 place full time equivalent nursery. A future extension of the school to accommodate 420 pupils has also been considered.

The existing building will be demolished, replacing a poor condition building with a smaller, much more efficient building. The decant of the existing school curriculum can be accommodated in the existing school so as to allow partial demolition. This would allow construction of the new build on or near the existing footprint.

The school design has been organised to facilitate a creative curriculum model with a wide variety of spaces, internally and externally. The plans will create a building for Hull rooted in the idea of Hullness. Endike Primary will be a community Beacon building, that respects the collective memory of Endike School and interprets this memory to create a powerful new image and identity.

May 2011
  • Phase 1; Works begin, this involves remodelling the existing West wing in order to house classes currently in the existing East wing
  • Temporary site compound and staff parking; set up and segregated from live school areas
  • Temporary safety partitions; erected between Central & West wing in order to separate live school areas from live works areas
View Images
June 2011
  • West wing remodel; Continued remodelling work on existing school building
  • East wing decant; removal and relocation of existing furniture and goods from East wing over to completed areas of the West wing
  • Temporary road; constructed from Endike Lane through to the rear of the West wing, accessing the temporary school car park
View Images
July 2011
  • East wing decant; complete decant of existing school premises/equipment
  • Phase 2; new school construction works begin
  • Site compound; created along with car parking facilities for construction operatives
  • Hoardings; erected around the construction works for safety
View Images
August 2011
  • East wing demolition; required as the new building sits within the same footprint
  • Drainage alterations; pipe work remodelled following demolition of East wing
  • Foundations; work starts with setting out and formation of piling mat
  • Archaeological watching brief; begins once piling mat excavation begins
View Images
September 2011
  • Pile foundations; commence and complete
  • Pile caps & ground beams; piles cropped and trenches excavated ready for concrete
View Images
October 2011
  • Pile caps & ground beams; works completed
  • Lift pits; excavated, shored, reinforced & poured
  • Under slab drainage; ducts & pipework commence
  • Steel frame; first delivery of steelwork arrives on-site
View Images
November 2011
  • Steel frame; erection of structural steel frame begins
  • Masonry; up to DPC begins
  • Ground floor; beam & block floor begins
  • Surface water drainage; ducts, pipe work & backfill commence
View Images
December 2011
  • Steel frame; erection of structural steel frame completes
  • Masonry; up to DPC completes
  • Ground floor; beam & block floor completes
  • Upper floors; framework, reinforcement & concrete pour begins to 1st floor & roof
View Images
January 2012
  • Upper floors; structural floors complete, curing period commences
  • External walls; SMS frame, insulation & membrane commences
  • Cladding; lettering features, rainscreen & render commences
  • Weathertight; Now areas within the building can begin
  • 1st Fix; sole plates, DPM, insulation & UFH pipework commences
View Images
February 2012
  • Roof; almost watertight, glazed rooflights begin as do fall pipes
  • External walls; SMS frame, insulation & membrane completes
  • Cladding; lettering features, rainscreen & render continues
  • External doors & windows; works begin
  • 1st Fix; screed to 1st floor, stud partitions begin
View Images
March 2012
  • Roofs; all items complete
  • Envelope; works continue
  • External floor tiling/paving; works commence around the school perimeter
  • 1st fix; Sprinkler pipes installed, plastering begins
  • Internal walls; all stud partitions complete
April 2012
  • External floor tiling/paving; works complete
  • Plastering; works complete
  • 2nd fix; M&E 2nd fix & suspended ceilings & vinyl commence
May 2012
  • 2nd fix; Mist coat applied to 1st floor
  • 3rd fix; including plumbing in of classroom sinks and installation of balustrades and handrails
  • External; Paving and plaza work begins
June 2012
  • 2nd fix; Kitchen fit out, balustrades & handrails, wall tiling commence
  • 2nd fix; Completion of suspended ceilings in classrooms
  • 3rd fix; Soft floor finishes commence
  • External; Cycle stand and shed bases put in place
July 2012
  • 2nd floor; Complete ready for decant
  • 1st floor; decorations complete, FF&E ongoing
  • Ground floor; big steps & slide feature fitted, decorations ongoing
  • Staircases; finishes ongoing
  • External; Caretaker shed, cycle stand, buggy store, signage, fencing and gates complete
August 2012
  • 1st floor; works complete ready for decant
  • Ground floor; works complete and ready for decant
  • External; access road to new building put in place & works around building completed
  • Drainage; connections made to main sewer
  • New school; ready for handover
September 2012
  • Building handover; and now in use
  • Phase 2; completed
  • Phase 3; commences
  • Client works; library fit out commences
  • Demolition; existing west and central wings islolated and demolition begins
October 2012
  • Phase 3; external works including grass pitches, gardens and MUGA commence
November 2012
  • Phase 3; erect climbing equipment and covered classroom, landscaping & paving continue
December 2012
  • Completion of all work