Project Timeline

Kingswood College of Arts is a new school that will specialise in art. This will be shown through the inclusion of new art rooms, dedicated space for resistant materials, a theatre and the art plaza entrance to the school.

Designed with the 'King' part of Kingswood in mind, the building features a crown-like roof and comprises of one four-storey building. Large, multi-use learning spaces can be used by a variety of subjects, and dining spaces of each floor are provided to encourage a range of healthy eating.

Part of the Kingswood College of Arts development includes community facilities, which will provide:

  • ICT facilities
  • library
  • a creche
  • meeting rooms
  • fitness and activity areas
  • family centred services
  • Business Conference zone

A theatre, which will be designed in conjunction with experts from Hull Truck, will be housed in the school. This will provide space for school and community productions, as well as seminars and conferences, all managed by an onsite Box Office.

Click here to view recent letters of thanks from the North Carr Area Committee.

May 2011
  • Site compound work
  • Archaeological and environmental surveys
  • Commence earthworks for building
View Images
June 2011
  • Install piling
  • Commence pile caps and ground beams
View Images
July 2011
  • Continue pile caps and ground beams
  • Commence car park areas
View Images
August 2011
  • Commence structural steel erection
  • Continue car park areas
View Images
September 2011
  • Continue structural steel erection including Precast flooring and liftshafts
  • Continue car park areas
View Images
October 2011
  • Continue structural steel erection including Precast flooring and liftshafts
  • Commnce external cladding support work
  • Commence roof
  • Complete car park area
View Images
November 2011
  • Complete structural steel erection including Precast flooring and liftshafts
  • Continue external cladding support work
  • Continue roof
  • Install windows and curtain walling
View Images
December 2011
  • Continue external cladding support work
  • Continue roof
January 2012
  • Complete roof
  • Install external cladding
  • Commence internal walls and partitions
  • Structural Steel Frame completed
  • M & E Commences
February 2012
  • Continue external cladding
  • Continue internal walls and partitions
  • Commence M & E installations
  • External wall cladding commences
  • CP Board completed
View Images
March 2012
  • Continue external cladding
  • Continue internal walls and partitions
  • Continue M & E installations
  • Roof coverings complete
  • Plant being lifted to the roof
View Images
April 2012
  • Complete external cladding
  • Continue internal walls and partitions
  • Continue M & E installations
May 2012
  • Continue internal walls and partitions
  • Continue M & E installations
  • £50m ordered through Morgan Sindall Hull Companies
  • Heat switched on
June 2012
  • Complete internal walls and partitions
  • Continue floor and wall finishes
  • Continue M & E installations
  • Power switched on
July 2012
  • Complete internal walls and partitions
  • Continue floor and wall finishes
  • Continue M & E installations
August 2012
  • Complete internal walls and partitions
  • Continue floor and wall finishes
  • Continue M & E installations
  • 100th apprentice employed on Morgan Sindall Hull BSF Schemes
September 2012
  • Completion of landscape works
  • Sample Schemes 1 year anniversary
October 2012
  • Completion of landscape works
November 2012
  • Completion of landscape works
December 2012
  • Early Completion
  • Building handover
January 2013
  • School SAD
  • Demolition of existing school building commences