Malet Lambert School Language College

Project Timeline

Malet Lambert School Language College, located at James Reckitt Avenue, Hull, currently has 1411 pupils on the school roll. The development will see this rise to 1500, plus 50 additional post 16 places.

The plans for this project involve part new build and part remodelling/refurbishment of the existing school. Hull Esteem Consortium proposes the construction of two new buildings on the school site.

The first will form a free standing dedicated indoor sports building. This will consist of a four court hall and activity studio, together with ancillary spaces including changing rooms and sport equipment storage. The changing room accommodation will serve both indoor and outdoor sports activities. The building will be constructed on the edge of the existing MUGA pitch.

The second building is proposed for alongside and connected to the original main building. This is a two storey structure, providing enclosure to the fourth side of each of the two original playground spaces.

The building will create a court to the west, covered by an ETFE roof, to become the heart space for the school community - to be used for dining, as a wifi-enabled cafe, for whole school assemblies, performances and community functions. A new library or LRC area will go in place of the existing dining area.

The new building itself will house teaching spaces for technology, business and enterprise, art, music and new drama facilities. General teaching spaces will also be provided.

As part of the plans, a new car park will be created to the west of the main building. The west playground will no longer be used for car parking, returning the playground to being a social space for pupils.

March 2011
  • Pre-construction enabling work
  • Creation of haul road
  • Start on erection of temporary fencing
View Images
April 2011
  • Site compound work
  • Commence work on all weather pitch and MUGA
  • Archaeological and environmental surveys
  • Continued earthworks for site enabling
View Images
May 2011
  • Temporary art department, fitness suite and drama studio facilities installed on site
  • Completion of enabling works
  • Start sports hall
View Images
June 2011
  • Decant of art department, fitness suite and drama studio to temporary facilities
  • Demolition commences of original art department, fitness suite and drama studio
  • Continued works on sports pitches
  • Continue Sports Hall
View Images
July 2011
  • Start on construction of new main building
  • Continue Sports Hall
View Images
August 2011
  • Temporary Kitchen
  • Continue new main building
  • Continue Sports Hall
  • All weather pitch and MUGA finished
  • Start existing building West refurbishment
View Images
September 2011
  • Continue Sports Hall internally
  • Continue New Main Building foundations and structure
  • Continue existing building West refurbishment
View Images
October 2011
  • Continue Sports Hall
  • Continue New Main Building foundations, structure, and roof
  • Continue existing building West refurbishment
View Images
November 2011
  • Continue Sports Hall towards completion
  • New main building start Forum roof, continue Cladding
  • Continue existing building west refurbishment
View Images
December 2011
  • Complete Sports Hall
  • Complete Forum Roof
  • Complete existing building West refurbishment
  • New main building continue internally
View Images
January 2012
  • School takes over Sports Hall, and existing main building west
  • Remove temporary HORSA fitness suite
  • Make New main building watertight & continue internal works
  • Start existing building East refurbishment
View Images
February 2012
  • New main building continue internal works
  • Existing building East continue refurbishment
  • West wing and sports hall handover
View Images
March 2012
  • New main building continue internal works
  • Existing building East complete refurbishment
April 2012
  • New main building continue internal works
  • Existing building Central commence refurbishment
May 2012
  • New main building, continue internal works
  • Existing building Central continue refurbishment
June 2012
  • New main building, continue internal works
  • Existing building Central continue refurbishment
July 2012
  • New main building, continue internal works
  • Existing building Central continue refurbishment
August 2012
  • Complete New main building
  • Complete existing building Central
September 2012
  • Completion of landscape works
October 2012
  • Completion of landscape works
November 2012
  • Completion of landscape works
December 2012
  • Final Completion