Winifred Holtby School & Tweendykes School

Project Timeline

We have rebuilt Winifred Holtby School on Midmere Avenue to now include the co-location of Tweendykes School.

The new state-of-the-art building provides 1,350 places for pupils aged from 11 to 19 and is fully equipped to provide 21st century learning opportunities.

"The BSF programme means high-quality, uplifting and fully functional buildings and here is just one example"

Teaching spaces have been grouped into 'learning suites' and offer a range of key facilities, including: learning spaces/classrooms, break-out spaces, resource management areas and storage, pupil resources, toilets, access to a range of dining/café areas and external teaching spaces.

There are high-tech indoor and outdoor sports facilities on site, including: the retention of facilities built under the New Opportunities Fund, a four court sports hall, a gymnasium, a health and fitness suite and a range of sports pitches. A brand new swimming pool has also been installed.

February 2010
  • The first work begins on the Winifred Holtby School Technology College & Tweendykes School project
  • Excavation started as the construction process began to take shape on the £38m project
  • Piling begins, helping to support the foundations by strengthening the soil under the building
View Images
March 2010
  • With work underway on the school, excavation work begins on other parts of the site
  • Clearing section two of works (Tweendykes)
View Images
April 2010
  • Demolish youth club: the existing youth club is demolished to make way for the sports hall and swimming pool
  • Steel structure: the steel structure continues to show good progress, as the upper floor begins to take shape
  • Frame construction: the structure takes on a shape and size clearly visible at a distance
View Images
May 2010
  • Completed ground floor block one - Winifred Holtby
  • Excavation of the swimming pool
  • On the roof of the school, planks have been installed
View Images
June 2010
  • Frame construction: with the framework being installed at a rapid rate, the school's steel structure continues to rise up from the foundations
  • Ground beams: ground beams are put in place throughout the floors of the school structure
  • Floor beams: floor beams for the Tweendykes part of the site are laid, ready for the next part of the framework to be installed
View Images
July 2010
  • Foundations are complete on the swimming pool
  • Steel structure: Part of the roof structure takes shape, as the final body of the structure becomes more visible
  • Roof steelwork: the first ETFE roof truss for the forum is installed
View Images
August 2010
  • External structure: window frames and panels are installed as the external structure transforms
  • Forum roof steelwork in progress
  • Winifred Holtby and Tweendykes steelworks complete. Block three sports hall slab installed
View Images
September 2010
  • ETFE Roof trusses completed
  • Internal partitions now commenced
  • M&E containment ongoing
View Images
October 2010
  • ETFE roof pillows installed and inflated.
  • Underfloor heating commenced
  • External cladding complete to Elevation D
View Images
November 2010
  • M&E roof top plant now in place
  • Metal decking to Sports Hall underway
  • Roofing to Swimming pool ongoing
View Images
December 2010
  • Internal partitions 2nd side boarding commence
  • Underfloor heating ongoing
  • Building officially watertight
View Images
January 2011
  • Suspended ceilings commence
  • First fix joinery ongoing
  • Painting and decorating works commence
View Images
February 2011
  • Lift installations commence
  • Lighting works commence
  • Wiring and electrical containment underway
View Images
March 2011
  • Floor finishes to main building underway
  • Installation of fire alarms and security systems
  • Fixed furniture installation works commence
View Images
April 2011
  • Floor finishes continue
  • Painting and decorating continues
  • Hard landscaping underway
May 2011
  • ICT works commence
  • M&E testing and commissioning
  • Energy Centre commissioning complete
View Images
June 2011
  • ICT works complete
View Images
July 2011
  • Witness testing of M&E services
August 2011
  • Preparing for handover
  • Loose FF&E installation
September 2011
  • Building handover
View Images